Seabras-1 Build Progress

Progress towards Ready for Service

100%

 

Marine Route Surveys

100%

Subsea Cable Manufacture

100%

Permitting and Licensing (Brazil)

100%

Permitting and Licensing (USA)

100%

Subsea Cable Installation

100%

Cable Station (Brazil)

100%

Cable Station (USA)

100%

USA Terrestrial Network

100%

Brazil Terrestrial Network

100%

USA POPs

100%

Brazil POPs

100%

 

With the marine installation of Seabras-1 completed on July 7th, the final phase of testing and acceptance of the system continues successfully.

All the terrestrial elements of Seabras-1 are now installed and commissioned. Overall system commissioning and final testing of the complete Seabras-1 network is nearing completion with a fully completed network deployment in mid August.

Activity remains intense for the Seaborn team in readiness for the ready for service date. Seaborn’s NOC is fully operational on a 24 * 7 basis and the entire Seaborn team is now in place and focused on the operation of the Seabras-1 network.